On November 28, 2019, the Technical Acceptance supervised by MGGP S.A. took place for the construction of the Hermanowice-Strachocina gas pipeline. This event marked the completion of the construction phase, with the next step being the gas filling of the pipeline.
The inspection was attended by representatives of OGP GAZ-SYSTEM S.A., the Investor of this project, as well as the Investment Supervision MGGP S.A., Author's Supervision ILF, and representatives of the Construction Contractor PGNiG Technologie.
The commission reviewed the transmission network facility and checked the documentation, concluding that the installation is ready for gas filling and commissioning.